
Overview
The Matter
Represented a defense electronics supplier before the Federal Circuit in an appeal from the Armed Services Board of Contract Appeals, which had sustained a termination for default on a multi-year production contract. The appeal turned on whether the contracting officer considered excusable delay attributable to a government-directed specification change before terminating. The Federal Circuit reversed, converted the termination to one for convenience, and remanded for determination of the client's settlement proposal.
The Contract and the Default Termination
The client held a production contract for ruggedized avionics components with delivery milestones running across three option years. Midway through the second option year, the agency issued a specification revision affecting a qualification test protocol. Deliveries slipped. The contracting officer issued a cure notice, then terminated for default eleven weeks later. The client's claim for excusable delay was denied, and the Board sustained the termination on the administrative record.
Excusable Delay Under FAR 52.249-8
The default clause excuses delay arising from causes beyond the contractor's control and without its fault or negligence, including acts of the government in its sovereign or contractual capacity. A termination decision that does not address a presented excusable-delay theory is not a discretionary judgment entitled to deference. The question on appeal was whether the record showed the contracting officer weighed the specification change at all, or whether the decision rested solely on the fact of late delivery.
Developing the Administrative Record
The Board proceeding involved roughly 2.1 million pages of agency and contractor documents, including qualification test data, engineering change correspondence, and the contracting officer's file. The team structured review to isolate the decision chain around the termination itself. That work surfaced the internal sequencing showing the specification revision preceded the delivery slip and was known to the contracting office before the cure notice issued. Those documents anchored the appellate argument.
The Federal Circuit's Ruling
The Federal Circuit reversed. The court held that the contracting officer's decision failed to address the excusable-delay theory the client had presented before termination, and that the Board erred in treating the omission as harmless. Because the government bears the burden of establishing the propriety of a default termination, and the record did not support it, the court converted the termination to one for the convenience of the government and remanded for determination of the client's termination settlement proposal.
Outcome and Significance
Conversion removes the reprocurement liability that accompanies a default termination and restores the client's eligibility posture on future solicitations. The ruling reinforces that a contracting officer's termination decision must engage a presented excusable-delay theory on the record rather than after the fact in litigation. The decision applies to any fixed-price supply contract where a government-directed change precedes the delay that prompts termination.
Engagement Details
The Specifics of This Matter
Every matter carries its own practical record, kept with the same rigor as the reasoning behind it. What follows are the specific facts of this engagement, not a preview of what any other matter might produce. Each case turns on its own particulars.
- Outcome
- appellate-ruling
- Resolution
- Won reversal at the Federal Circuit of an Armed Services Board of Contract Appeals decision sustaining a termination for default against a defense electronics supplier. The court held that the contracting officer's failure to consider excusable delay under FAR 52.249-8 rendered the termination decision arbitrary, converted the termination to one for convenience, and remanded for determination of the client's termination settlement proposal.
- Geography
- CO, US
- Resolved
- March 11, 2026
- Duration
- 52 months
Past results do not guarantee, warrant, or predict a similar outcome in any future matter. Every engagement is unique and must be evaluated on its own facts and circumstances.
Clarity before commitment.
Facing a Disputed Bid Award?
Public bid protests turn on the specific solicitation and the statute governing that procurement, not on how a past matter resolved. Our team weighs the record before recommending whether a protest is worth pursuing, and prepares each filing with the agency's likely position in mind. If your organization is facing a procurement award it believes was mishandled, our commercial litigation team welcomes the chance to discuss the facts of your situation.